Of Australia's 32 biggest infrastructure projects, just eight had a public business case

  • Written by: Marion Terrill, Transport and Cities Program Director, Grattan Institute

Politicians love the vote-pulling power of major transport projects. They also quite like to keep details of of how they’ve decided to fund a project under wraps, avoiding the pesky scrutiny the public deserves.

Of 32 projects larger than A$500 million Australian governments have committed to since 2016, the Grattan’s Institute’s analysis[1] shows just eight had a business case either published, or assessed by a relevant infrastructure body at the time money was committed.

A business case documents the essential elements of an argument that a particular project is worth building, and is the best available option to solve a specific problem.

Business cases should be essential to any government considering a large spending commitment. They enable decision makers to establish whether a particular project (or other policy) is a worthwhile investment, and if it is more worthwhile than alternatives. It is reprehensible that federal and state governments so often decide to invest in major projects without publishing such assessments – and often without doing them.

Even the biggest lack business cases

Size is no barrier. There was no published business case at the time of commitment even for the biggest $5 billion-plus projects, such as the 24 km Sydney Metro West[2] rail tunnel between Sydney’s CBD and Parramatta, the Melbourne Airport Rail[3] and the 10 km Torrens-to-Darlington[4] section of Adelaide’s North South Corridor.

This means politicians committed to these projects without being willing to share – or even without knowing – if those projects are in the community’s interest to build, let alone if they are the best choice for the money.

Of Australia's 32 biggest infrastructure projects, just eight had a public business case CC BY-SA[5] Most of these 32 projects received federal as well as state funding. Of the 22 large projects to which the federal government has committed a contribution since 2016, just six had a business case published or assessed by Infrastructure Australia, the federal agency established in 2008 to provide independent advice to governments on infrastructure. Of the 16 projects without business cases, 14 were listed as “initiatives” on Infrastructure Australia’s priority list[6], indicating they had “the potential to address a nationally significant problem or opportunity”. But their assessment had not yet been completed when committed. Read more: WestConnex audit offers another $17b lesson in how not to fund infrastructure[7] The remaining two projects are Stage 2 of the Monash Freeway Upgrade[8] in south-east Melbourne, and the Albion Park Bypass[9] on NSW’s Princes Highway, south of Wollongong. These two projects, worth more A$2 billion between them, had not appeared on any Infrastructure Australia priority list at the time the state governments committed to them. As Infrastructure Australia put it in a 2018 report on decision-making principles[10]: “Too often we see projects being committed to before a business case has been prepared, a full set of options have been considered, and rigorous analysis of a potential project’s benefits and costs has been undertaken.” Of Australia's 32 biggest infrastructure projects, just eight had a public business case Prime Minister Scott Morrison and Victorian Premier Daniel Andrews at press conference in March 2018 announce a combined $10 billion in funding to build a rail link to Melbourne Airport. Stefan Postles/AAP Cases after the facts It’s true that 11 major transport projects ended up with a business case later on. Just last month, for example, the Victorian government released the business and investment case for the first stage of its massive Suburban Rail Loop[11], expected to cost $30 to $34 billion — three years after it announced its commitment to the project. We’ve also seen business cases after the decision to invest on Stage 1 of Sydney’s F6 motorway, several sections of Queensland’s M1 Pacific motorway, and on Tasmania’s biggest project, the $500 million Bridgewater Bridge[12] across the Derwent River in Hobart. Of Australia's 32 biggest infrastructure projects, just eight had a public business case Tasmanian Liberal senator Eric Abetz, state treasurer Peter Gutwein and Liberal MLC Jane Howlett with Prime Minister Malcolm Turnbull at a press conference in June 2018 to announce funding for a new Bridgewater Bridge in Hobart. Rob Blakers/AA{ Too much secrecy It isn’t just business cases where there is a lack of transparency. Information about tender processes – who bid, who won, by what process, and the contract value – is not routinely published in Australia. Even when it is, it can be hard to find. The Grattan Institute’s research[13] shows NSW discloses more information than other states, publishing contract and tender information as a matter of routine in a central register. Queensland discloses the least information, and less of what it does publish is available in a central location. Politicians may defend their secretive practices by pointing out they are elected to make decisions. But even those who you might imagine would be most likely to side with governments in preferring the shadows — those who build and advise the big projects – disagree with this. In August the Grattan Institute hosted a webinar with two respected representatives of construction companies, Acciona Geotech’s Bede Noonan and McConnell Dowell’s Chris Lock, and an expert legal adviser, Infralegal’s Owen Hayford. All emphatically agreed governments should have and make public business cases – at the very least. Read more: Budget infrastructure spending serves mainly political goals[14] Not only was this a question of public accountability, they argued, but an opportunity to persuade the community of the merits of a proposal, and a chance to bring in more innovative ideas. They are right. Transparency is not everything, but it is important. Governments should publish it all: business cases, tender documents, contract values, the basis on which claims for major projects are settled, evaluation criteria, post-completion reviews. Politicians should welcome the scrutiny. In these fractured times, transparency builds trust. A video of the Grattan Institute’s webinar “How to get better bang for our transport project bucks” is avaialable here[15].

References

  1. ^ Grattan’s Institute’s analysis (grattan.edu.au)
  2. ^ Sydney Metro West (www.sydneymetro.info)
  3. ^ Melbourne Airport Rail (bigbuild.vic.gov.au)
  4. ^ Torrens-to-Darlington (dit.sa.gov.au)
  5. ^ CC BY-SA (creativecommons.org)
  6. ^ priority list (www.infrastructureaustralia.gov.au)
  7. ^ WestConnex audit offers another $17b lesson in how not to fund infrastructure (theconversation.com)
  8. ^ Monash Freeway Upgrade (roadprojects.vic.gov.au)
  9. ^ Albion Park Bypass (roads-waterways.transport.nsw.gov.au)
  10. ^ decision-making principles (www.infrastructureaustralia.gov.au)
  11. ^ Suburban Rail Loop (suburbanrailloop.vic.gov.au)
  12. ^ Bridgewater Bridge (www.transport.tas.gov.au)
  13. ^ research (grattan.edu.au)
  14. ^ Budget infrastructure spending serves mainly political goals (theconversation.com)
  15. ^ here (grattan.edu.au)

Authors: Marion Terrill, Transport and Cities Program Director, Grattan Institute

Read more https://theconversation.com/of-australias-32-biggest-infrastructure-projects-just-eight-had-a-public-business-case-166847

The Weekend Times Magazine

Turning fashion into power - Beauty with Brains

During this unfortunate time of our lives there’s a hidden gem business which keeps the hopes up for many lives of women of all walks of life. Fashion...

How TPD Solicitors Unlock Your Super Insurance Payout Fast

Up to 70% of Australians don't realize they have TPD insurance through their super, potentially missing out on life-changing payouts when they need them most. This staggering statistic reveals a...

What Happens During a Rental Property Inspection?

The rental property inspection is one main factor that sometimes leaves tenants wondering a lot of things. Though it might occasionally feel like a scary procedure, it is a lot...

The Best Luxury Cars in 2021

The best luxury cars that you can look out for this year. You are probably looking for the most comfortable car this year. You go for these types of cars...

Dark Mode Emails: How to Design for Visibility and Impact

Image by DC Studio on Freepik With dark mode rolling out on various devices and email service providers, the need for emails to render correctly and legibly is vital. Dark mode...

What’s the Difference Between a Caravan & A Motorhome?

Australians love the freedom of the open road, and choosing the right setup can make travelling safer and far more enjoyable. With both caravans and motorhomes growing in popularity and...

Car Removal Melbourne and Clearing Vehicles the Easy Way

Unwanted vehicles can quietly become a problem, occupying space, losing value, and creating unnecessary stress. Car removal Melbourne offers a practical way to deal with cars that are no longer useful...

Does Sydney Australia Have a Good Nightlife Scene?

In the last several years, Sydney's nightlife has changed dramatically. The New South Wales state government adopted Draconian lockout regulations in 2014, forcing city center venues to close their doors...

Planting The Seed To Health Living Top tips on planting for wellbeing

With the family home full time and a need to keep everyone busy, it is the ideal time to plant a seed to a healthier lifestyle. Tuscan Path Product Manager...